News

Construction &
Titles Update

Phases of Construction Breakdown

1. Plans & Permits

Council and Authority acceptance of documentation including engineering design to allow physical works to commence on site.

2. Earthworks

Preparation of the site to achieve design lot levels including site scrape, shaping of the existing ground and construction of retaining walls if required.

3. Sewer & Drainage

Installation of sewer and drainage to service the development of the stage.

4. Road boxing, Kerb & Channel

Prepare the ground and start to construct the lower layers of the road pavement. Install water and gas mains and construct kerb and channel.

5. Electrical & Telecommunications

Trench and install electrical and telecommunication services once kerb and channel works are complete.

6. Footpaths & Asphalt

Prepare the ground in readiness to construct footpaths. Construct footpaths and topsoil nature strips. Construction of middle pavement layers and placement of asphalt.

7. Completion & Inspection of Works

Council and Service Authority works inspections and sign off to constructed works including roads and services. Provision of nal documentation to Council to facilitate a Statement of Compliance for the development stage.

8. Titles Office & Settlement

Registration of individual lots from each stage occurs at the titles office, and your block is now ready for you to settle & start the construction of your new home. Congratulations!

Full construction update
Stage 4: Titled -
Stage 5: Titled -
Stage 6: Phase 3: Sewer and drainage
Stage 7: Phase 3: Sewer and drainage
Stage 8: Phase 3: Sewer and drainage
Stage 9: Phase 3: Sewer and drainage
Stage 17: Phase 1: Plans and Permits
Stage 18: Phase 1: Plans and Permits
Title Information Forecast
Anticipated Constructions Start Forecast Titles
Stage 1: Construction Completed Titled
Stage 2: Construction Completed Titled
Stage 3: Construction Completed Titled
Stage 4: Construction Completed Titled
Stage 5: Construction Completed Titled
Stage 6: Construction Commenced July 2019
Stage 7: Construction Commenced August 2019
Stage 8: Construction Commenced September 2019
Stage 9: Construction Commenced September 2019
Stage 17: November 2018 May 2020
Stage 18: December 2018 May 2020
We will continue to keep you updated on construction progress onsite. We note that delays can be caused by circumstances beyond our control, such as weather, but we will do all we can to minimise their impact. UPDATED: ARPIL 2019